|
WSWS : News
& Analysis : Europe
: Ireland
Irish smallholders jailed for opposing gas pipeline
By Steve James
30 August 2005
Use
this version to print
| Send this
link by email | Email
the author
For almost eight weeks, five men have been incarcerated in
Dublins Cloverhill jail for opposing compulsory acquisition
orders taken out for the construction of a multi-billion-euro
gas pipeline and terminal.
The five, Micheal OSeighin, Willie Cordruff, Brendan
Philbin, Philip McGrath and Vincent McGrath are far from being
left-wing activists. They are small land owners and residents
of the Erris peninsula in County Mayo, in the isolated far west
of Ireland. But they have been subjected to such harsh treatment
because their actions have interfered with a project that will
bring millions in tax revenues to the Irish government and enrich
substantial sections of the Irish bourgeoisie in the process.
For this reason they are being made an example of what will happen
to those who defy the major corporations on whom Irelands
economy depends.
The mens jailing is the culmination of a protracted dispute
between energy corporations working closely with the Irish government
on one side, against an alliance of smallholders, local politicians,
environmental organisations and safety groups.
The jailed men insist that the gas terminal is being built
in disregard for normal health and safety procedures. The disputed
pipeline and terminal are intended to collect and process gas
from the new Corrib field, which lies around 70 kilometres off
Irelands west coast and is estimated to hold between 5 and
7 trillion cubic feet of natural gas, worth between 15 and 21
billion euros.
Discovered in 1996, the field lies in deep water, 355 metres,
in the Atlantic Margins area of the sea floor off the west coast
of the British Isles. Drilling in the Atlantic Margin has been
increasing in recent years as global oil and gas reserves have
declined, prices have increased, and new technology has made previously
uneconomic reserves potentially worth exploiting.
Other reserves have been discovered in British-controlled areas,
and the entire region is thought to be potentially lucrative,
although technically difficult to exploit due to the deep water
and bad weather conditions.
Gas from the Corrib field is intended to be injected at one
end of the emerging European and Russian gas distribution network,
whose primary purpose is to provide gas for the huge energy demands
of the European Union. Two gas interconnectors already cross the
Irish Sea to allow export to Europe.
The Corrib plan is also seen as an important part of the development
of an all-Ireland energy infrastructure, which includes cross
border pipelines into Northern Ireland and a gas ring main
intended to supply gas to most areas of the island. Until now,
Ireland has never had many indigenous power resources beyond those
provided by peat bogs and small number of narrow seamed coal mines.
Even after the development of hydropower and some discoveries
of natural gas in the 1960s, 85 percent of energy requirements
are imported, mostly via the UK.
The project to extract the Corrib gas is co-owned by Shell,
via the formerly Irish state-owned Enterprise Energy, as well
as the Norwegian Statoil company and US-owned Marathon Oil. Development
costs are estimated at around 700 million euros.
In order to make the project viable, the developers have proposed
that rather than being processed at sea, untreated gas would be
piped at high pressure to an onshore processing terminal. Gas
processing at an offshore wellhead requires expensive rigs and
a large and highly qualified workforce. An onshore terminal is
cheaper to build and operate, while the wellhead can be maintained
from the oil companies existing operations in Scotland.
A mere 27 workers are expected to be needed to run the onshore
terminal. The companies argue that without this technique, the
project will not be profitable and will not go ahead.
Opponents of the development say there are serious safety concerns
and are demanding that an offshore terminal be utilised.
They argue that the high-pressure 92 kilometre pipe, pumping
nine kilometres inland at between 150 and 300 Bar (compared with
a domestic gas pressure of 4 Bar) is dangerous to those living
in the immediate environs. The proposed terminal will also house
huge gas storage facilities and will require the removal of thousands
of tonnes of peat bog in an area of outstanding natural beauty.
Originally intended to be completed in 2003, the Corrib project
has been repeatedly put back while successive planning enquiries
and investigations at county and national level have been carried
out.
In 2003, An Bord Pleanála, the Irish planning authority,
following extended hearings, refused planning permission on the
grounds that transferring 650,000 cubic metres of bog was too
dangerous due to possible slippage. In response, the Irish government
threatened to introduce legislation to allow critical infrastructure
projects to be pushed through.
In the end, the bog was dumped in another nearby location that
was accepted by Mayo County Council, despite a serious landslip
in the intervening period, which, had the pipe been in operation,
could have ruptured it.
In October 2004, An Bord Pleanála approved the project.
Shell implemented compulsory acquisition orders on 35 plot
holders whose land lay on the route of the proposed pipeline to
the terminal. Twenty-eight of the land holders had previously
agreed to give up their land. The remainder, whose land constituted
50 percent of Shells requirements, refused to comply. Police
were called on a number of occasions following some minor confrontations
between the smallholders and Shell officials.
Earlier this year, Shell was granted an injunction to prevent
the smallholders from continuing to prevent pipe-laying operations
on their land. The smallholders continued to oppose Shell and
five were imprisoned in July for contempt. Shell promptly started
work.
The jailings have shocked large numbers of people in Ireland
and generated widespread protests. In July, 1,500 people rallied
in Galway to protest. Supporters of the development have also
been alarmed. Chris Tallott, a member of a local group which campaigned
for the terminal on the basis that it would provide a much needed
economic stimulus to an isolated and impoverished region, told
the Irish Times, I know these five men. I regret
very much what has happened, and perhaps it has wakened us up
to reality.
The issue is becoming a focus for more general distrust of
the Fianna Fail/Progressive Democrat coalition government and
has been successfully utilised by its political opponents. In
response, Shell has been instructed by Dublin to dismantle part
of the pipeline it had started to build in advance of full approval,
and has announced a programme of dialogue to build
support for the scheme.
But to date Shell has not lifted its court injunction against
the five. And the court has insisted that the five must first
purge their contempt and agree to obey the court order before
being freed.
The government has since awarded exploration licences to Shell
and a number of other energy companies for an area of over 15,800
square kilometres to the north of the Corrib field.
See Also:
Irelands dilemma after
rejection of European Union budget
[30 June 2005]
Top of page
The WSWS invites your comments.
Copyright 1998-2008
World Socialist Web Site
All rights reserved |